Cavity Brick
Insulation Installation Instructions
1. Inner skin is constructed to 1200mm high with brick ties installed.
2. Foilboard Spacer Block fixed over ties to maintain cavity space (not essential).
3. Horizontally installed, panel is pushed over brick tie (centre of cavity).
4. Tape all joins and any gaps in material.
5. Continue outer skin up to 1200mm.
6. Repeat steps 1 to 5.
Instructions are merely a guideline only and should be interpreted with consideration for the specific building application. Alternative installation methods may be implemented. Safe installation practices are encouraged at all times. Please contact Foilboard Australia Pty Ltd for further information.
Handling and Storage
It is recommend that if the product is being stored for extended periods it should be kept clean and dry. Any moisture present between sheets should be dried to prevent potential oxidization and must not be stored with either foil surface in contact with any alkaline materials.